All Pages · Sales Orders · 26-27_04_001
RP

26-27_04_001

Urgent In Progress

Acme Engineering Pvt Ltd · 3 line items · committed 25 May 2026

Customer

Acme Engineering Pvt Ltd
R. Sharma · +91 98765 12345
GSTIN 27AABCA1234D1Z2

Dates

Order date
04 Apr 2026
Committed
25 May 2026
Customer PO
PO-2026-0421

Assigned

Planner
Sneha Iyer
QA
Mahesh Kulkarni

Line items (3)

Overall progress: 47%
#ItemDrawingQtyUnitRequiredJob CardsProgress
1Hydraulic Shaft 32mm
ITM-1001
DWG-201/Rev-3100Nos10 May10 cards · 6 done
60%
2Flange Cover Plate
ITM-1015
DWG-415/Rev-150Nos15 May5 cards · 2 done
40%
3Mounting Bracket
ITM-1022
DWG-318/Rev-240Nos20 May4 cards · 1 done
25%

Activity timeline

  1. 04 Apr 2026 · 10:14
    SO created by Sneha Iyer
  2. 05 Apr 2026 · 14:30
    Job cards defined for all 3 line items (19 total)
  3. 06 Apr 2026 · 09:00
    Released to shop floor
  4. 22 Apr 2026 · 16:48
    Item 1 — Operation 2 (Milling) completed for batch 5
  5. 02 May 2026 · 11:20
    Item 1 — 6 batches fully completed