All Pages · Dashboard · Job Status Tracking
RP

Job Status Tracking

Drill down on any job card across all operations

JC-26-27_04_001-1-002 High In Progress

Hydraulic Shaft 32mm · Batch 2/10

Acme Engineering Pvt Ltd · SO 26-27_04_001 · Due 10 May 2026

ETA
06 May, 11:30
on track
Overall progress2 of 4 operations · 50%
  1. Op 1 · Turning on LATHE-01
    Completed
    Anil Mishra · 02 May 2026 09:30 → 10:48 · 1h 18m · Qty: 10/10 good
  2. 2
    Op 2 · Milling on VMC-01
    In Progress
    Suresh Kumar · started 04 May 13:50 · elapsed 42m · 5/10 done
  3. 3
    Op 3 · Grinding on GRIND-01
    Pending
    Estimated 1h 0m · expected start 04 May 15:30
  4. 4
    Op 4 · Inspection on QC Bench
    Pending
    Estimated 30m · expected start 06 May 11:00

Activity log

  1. 04 May 14:325 of 10 pieces completed on Op 2
  2. 04 May 13:50Op 2 started by Suresh Kumar on VMC-01
  3. 02 May 10:48Op 1 completed · 10/10 good
  4. 02 May 09:30Op 1 started by Anil Mishra on LATHE-01
  5. 01 May 16:00Job released to shop floor
  6. 01 May 14:30Job card defined by Sneha Iyer

Quality summary

15
Good pieces
0
Rejected
5
Pending

No quality issues recorded for this batch yet.