Job Status Tracking
Drill down on any job card across all operations
JC-26-27_04_001-1-002
High
In Progress
Hydraulic Shaft 32mm · Batch 2/10
Acme Engineering Pvt Ltd · SO 26-27_04_001 · Due 10 May 2026
ETA
06 May, 11:30
on track
Overall progress2 of 4 operations · 50%
-
✓Op 1 · Turning on LATHE-01CompletedAnil Mishra · 02 May 2026 09:30 → 10:48 · 1h 18m · Qty: 10/10 good
-
2Op 2 · Milling on VMC-01In ProgressSuresh Kumar · started 04 May 13:50 · elapsed 42m · 5/10 done
-
3Op 3 · Grinding on GRIND-01PendingEstimated 1h 0m · expected start 04 May 15:30
-
4Op 4 · Inspection on QC BenchPendingEstimated 30m · expected start 06 May 11:00
Activity log
- 04 May 14:325 of 10 pieces completed on Op 2
- 04 May 13:50Op 2 started by Suresh Kumar on VMC-01
- 02 May 10:48Op 1 completed · 10/10 good
- 02 May 09:30Op 1 started by Anil Mishra on LATHE-01
- 01 May 16:00Job released to shop floor
- 01 May 14:30Job card defined by Sneha Iyer
Quality summary
15
Good pieces
0
Rejected
5
Pending